JBJI Propylene - Increase of production capacity / Refinery Porvoo

Customer: Borealis Polymers Oy

Country: Finland

Period: March – September 2017
Turnaround: 30. August – 29. September

Services:

  • Process planning, pre-fabrication, dismantling, pre-turnaround activities, installation during turnarouned, annealing, coating, pressure testing and documentation 
  • Equipment: 65 t dismantling & 30 t installation
  • Steel construction: 40 t
  • Piping system: 70 t dismantling and 290 t installation
  • Material: SA106B  / SA333-6,  TP316L /  TP321
  • Welding seams: 10.000/ TA 2:000 (ø 5“)
  • 108.000 DI‘s / TA 20.100 DI‘s
  • Isometry:215 dismantling, 645 installation