Thermal power plant Eemshaven / Netherlands

Customer: RWE Power AG
Supplier: Konsortium Babcock Borsig Service GmbH / MCE Energietechnik GmbH/BIS VAM

Services Konsortium MCE ET/BIS VAM:

  • Detail engineering, supply, prefabrication and instalaltion incl. commissioning and trial run
  • Weight pipe material: 391 t
  • Weight valves: 36 t
  • Weight support incl. steel construction: 130 t
  • Dimensions: DN 25 up to DN 900
  • Material: P235GH, CrNi Material, PP

Period: May 2008 – May 2013
Installation period incl. pre-fabrication: April 2011 – December 2012